After almost a full week of digging down various types of tubing and pipes we have the sewer system done, the new water well is connected and we ready for the electric company to connect our house to the grid. Very happy to be done with this work.
Connecting the water well
The drilled water well is about 25 meters away from the house. It was drilled a few weeks ago but in order to get water from it we need to connect it with piping as well as electricity for the deep water pump.
The connections coming out below the workshop on the southern side.
The trench where the water pipes will be placed is 1 meter below ground to be safe from freezing.
The 1 meter deep trench towards the southern facade of the workshop.
The complete trench stretching from the workshop to the borehole on the far left in the image.
The steel pipe from the borehole sticking up.
The 50mm yellow tube for electricity and the dark water pipe next to it.
The trench all covered up.
Preparing for electricity & Internet
Once done with putting down the water pipe to the well we started the longs dig of them all; digging a trench for the electricity going from the workshop all the way down to the main road. In total this was about 120 meters of digging.
The west side of the workshop where the electricity and internet will be connected to.
We’re digging down 3 different pipes. The large yellow pipe is a 110mm wide pipe for the main electric connection. The small 50mm yellow pipe is for future lighting and/or an electric gate at the property entrance. And last, the green 50mm pipe is for internet fiber that we hope to get installed at the same time as the electricity.
The 3 pipes in place, ready to be covered up with dirt.
To avoid all tree roots we opted for digging in the middle of the road when possible.
About half way down the road.
The end of the trench. Finally here. Only thing left is to cover it up with dirt.
Final thoughts
It’s been a tough week, hot weather with lost of digging but we managed to get a lot done in just a week. The sewer system is ready to start using, the water well connecting is prepared for next step and both electric and fiber internet installation is one step closer to reality.